The Buyer declares that
SITE INSPECTION & ASSESSMENT | PRE-INSTALLATION | INSTALLATION | INSPECTION & CONNECTION |
---|---|---|---|
1 TO 2 DAYS(1) | 1 TO 2 WEEKS(1) | 1 TO 2 DAYS(1) | 2 TO 8 WEEKS(1) |
Our consultant will be in
contact with you (“The
Buyer”) to schedule a day for
the site inspection, to collect
information and assess the
roof, switchboard, and
meter.
What is expected of you? To schedule a date forthe inspection. • To be available at the premise for the site inspection and give full access to our consultant to assess the site for the installation. Discuss with the consultant about the placement of panels on the roof and the placement ofthe inverter. Our consultant will walk you through the system and pricingdetails by presenting this Contract to you. |
Our consultant or Installation
coordinator will schedule a
date and time for your
installation and will be in touch
with you to advise of the same
What is expected of you? • To schedule a date and time for the install, with our consultant or Installation Coordinator. • To clear the driveway on the day of the install, before the scheduled installation time, for unloading the solar panels and other materials required for the install |
Our installation team arrives at
your property at the previously
agreed time and date, and the
estimated installation date
(Target date) would be within 8
weeks from contract signed
date. What is expected of you? • To be available on the day of the installation and give full access to the installation team to the switchboard, meter androof area. • To provide the installation team with certain information that they may need on the day to complete the installation and sign the connection and completion form. |
Once the installation is
complete, we will notify an
Electrical Inspector accredited
by Electricity Safe Victoria, that
the installation is completed.
The Inspector will then inspect
the new system and issue the
Certificate of Electrical Safety.
Once the Certificate of
ElectricalSafety is issued, it will
be sent toyour electricity retailer
and distributor to notify them of
the new solar system
The Electricity retailer and distributor can take up to 6-8 weeks to process this paperwork and issue you the new rates and Feed-In-Tariff offer. (2) Please make sure that you reviewthe new electricity rate and feed-in-tariff rate offered by your electricity retailer before you accept their offer. |
1 Estimated timeframe may varies due to multiple reasons beyond our control, Please refer to “Delivery and Installation” clause (Commercial Solar installation may take longer period to complete due to system size)UNITED ENERGY’ GRPOUP's Terms and Conditions. |
2 Your current electricity contract/tariff may change following installation of solar and you should contact your electricity retailer: |
a.before signing a contract, to check what new electricity tariff rates may be applied; and |
b.after installation of the solar PV system, to confirm that the agreed tariff has been applied. |